Hamlin School CTE Addition

Category
current-projects

Address:
44577 188th St.
Hayti SD

SF: 30,000+ SF
Owner: Hamlin School District
Designer: CO-OP Architecture
Delivery Method: CMR

During the month of March, Ron and his crew continued to erect the structural steel for Buildings B & C along with starting the roofing and siding.  The blocking at the roof was also recently installed along with the roofing repairs at the tie-in from the existing building to Building A.  With the completion of the concrete floor in Building A, the masonry and steel stud subcontractors have been working on framing walls.  Above ground rough ins are underway following the framing of the walls.  Underground work has also been started and will be ongoing in Buildings B & C as it is prepped for the upcoming concrete floor pours.